Notice to owner

FloridaNotice of Intent to Lien

I submitted an NTO for a project that started 12/7/22 - 12/27/22. However, through change orders, the project has continued through 4/24/23. My last payment was through 3/2/23. do I need to submit a new NTO or file a lien?

2 replies

May 31, 2023

Change orders are by statute part of the contract. Only one NTO is required under those circumstances. Your next step is to file a construction lien within 90 days of completing your work. File sooner rather than later.

0 people found this helpful
Helpful
Jun 6, 2023

No need to refile an NTO. It is time to record a claim of lien. Contact a construction attorney to prepare the lien for you.

0 people found this helpful
Helpful