my 90 days are today..If I send a 10 Day Intent to lien letter, do I get 10 more days to file my Mechanic's Lien?

1 reply

May 29, 2018
Nevada is one of the few states that has statutory requirements surrounding a Notice of Intent to Lien. In Nevada, a 15-day Notice of Intent to Lien is required, and that Notice of Intent to Lien extends the lien deadline by 15 days. It's a little more in depth than an ordinary Notice of Intent to Lien as well - it must incorporate substantially the same information as the required lien filing.
0 people found this helpful
Helpful

Add your answer or comment

Not the answer you were looking for? Check out other Notice of Intent to Lien topics or ask your own question