If my contractor did not pay the subs can the subs file a mechanics lien against me. I think my contractor owes the subs as he told me he is struggling
If the subcontractors served a notice to owner on you within 45 days of beginning their work at the property, then the answer is probably yes. You should ask your general contractor for a list of subcontractors and before you pay him again, you should ask for lien releases from those subcontractors. There are statutes under Chapter 713, that can also help you obtain this information.