Menu
Home>Levelset Community>Legal Help>Was charged over $5000 for extras and was not notified. Can this happen without a change order?

Was charged over $5000 for extras and was not notified. Can this happen without a change order?

WisconsinConstruction ContractPay Applications

Does a general contractor required to fill pou a change order in Wisconsin? Or do they need to notify amounts and materials not in quote?

2 replies

Nov 10, 2020
A change order is not required but probably a good idea. The question is whether there is a legit agreement or contract between the parties for the extras. You can have an oral contract or written contract for extras. A written contract whether it's called change order or otherwise is going to be easier to enforce.
0 people found this helpful
Helpful
Nov 10, 2020
I have the same question as well. The proposal does state we would be charged for extras but I could they proof that I asked for extras or they just placed themselves
0
Report Spam

Add your answer or comment

Not the answer you were looking for? Check out other Construction Contract topics or ask your own question