ColoradoLien Deadlines

Which is the date that is required for the lien? Substantial completion? Full completion?

1 reply

Jun 9, 2020
Colorado's mechanics lien deadline is generally 4 months after the last furnishing date. However, for laborers, this deadline is adjusted to 2 months after the completion of the improvement. Levelset discusses the difference between those two dates here: Confusing Dates: What’s the Difference Between Date of Last Furnishing and Date of Substantial Completion?
0 people found this helpful
Helpful

Add your answer or comment

Not the answer you were looking for? Check out other Lien Deadlines topics or ask your own question