We have a customer who we worked their insurance claims for 2 properties have the claim information and now customer will not return our calls to move forward. We want to know the timing we have for filing liens....Read More
An incorrect General Contracting Company was listed as a General under "Project Stakeholders" in addition to the correct General Contractor, who was listed as "We were hired by". The General that was listed incorrectly contacted me to let me know they were not the General for this project. Does this Notice need to be corrected and resent or because the correct General was listed under "We were hired by", is it okay?...Read More
Already sent a Notice of Intent to Lien; however, we missed the window to actually file a Lien. At this point, we would like to send an official Demand Letter....Read More
We just got a subcontract from a general contractor for plumbing work. In the contract it states that we waive the rights to file any type of lien against them. Is this illegal? ...Read More
Can we still file a mechanics lien on this job? Are we legally able to send a notice of intent to lien at this time? This customer is non responsive and we need to take further action at this time. Please provide advice...Read More
I'm a small upstart Landscaping company i completed a job client made initial payment after job completion. Client is now refuing to pay the rest of owed money. ...Read More
I am filing a second pay application and I billed for stored material on the first application. We used some of the material during the period and I am unsure what column to move the used amount to. Would you move it to column D or E?...Read More
A major new window contractor installed the wrong windows in my home but is demanding full payment.
Documents clearly show windows ordered are not those installed.
They are threatening a lien.
Thank you...Read More
In the state of Ohio – when we do work for a General Contractor – are we required to request a Notice of Commencement from the GC and are we required to submit to the GC a Notice of Furnishing within 21 days of providing labor or materials for the job?...Read More
We have a contract with someone as their GC. They are not holding retainage on us for this project. Am I able to still hold a retainage of 10% on the subcontractors that we have on the job?...Read More
Yes I had a customer suddenly change his mind and say he was putting a hult to a job that I had just basically started for him the customer and he didn’t offer to buy the contract out from me or anything and just expects me to walk away but there are damages he’s caused me by doing such 1) bills are going to be behind 2) Christmas for my family is now ruined pretty much to say with this unexpected lose of income that the customer has caused me ...Read More
We have filed a lien and now need to to send an intent to foreclose letter. Is this something provided by Levelset. How long do we have file to foreclose in Ohio once the lien is filed?...Read More